Deadline Activity
May 8, 2014 Proposals due to TDA, end of business day
June 12, 2014 Potential sub-recipients notified of project state approval status
June 20, 2014 Approved projects submit additional information (if requested)
October 1, 2014 Federal funds become available.
October 6, 2014 Sub-recipient will receive notification of project approval status

 

Timeline for Approved Projects
2015
April 1, 2015 Quarterly Update Due
July 1, 2015 Quarterly Update Due
Oct. 1, 2015 Quarterly Update Due
Dec. 1, 2015 Annual Report Due
2016
April 1, 2016 Quarterly Update Due
July 1, 2016 Quarterly Update Due
Oct. 1, 2016 Quarterly Update Due
Nov. 21st 2016 Annual Report Due
2017
April 1, 2017 Quarterly Report Due
July 1, 2017 Quarterly Report Due
September 30th, 2017 Grant Period Ends – all funds must be used by this date
October 31st, 2017 Final Report Due
Projects can be completed prior to final report deadline with all supporting documentation being submitted within 30 days of project completion.